FEATURED PROJECTS
Hydro-Technologies' Fast Track Hydro-Demolition Projects
OHIO: Project 990205 Hamilton Co., Highway 27 and
Brehm Road over I-275 in Cincinnati, Ohio.
Description: Performed Total Surface Preparation using Hydro-Demolition
on 4,010 square yards of bridge deck surface. Placed a new Latex Concrete
wearing surface.
TENNESSEE: Project 5775 Shelby Co.,
Description: I-40 Ramps on the I-40 Mississippi River bridge.
Description: Perform Total Surface Preparation using Hydro-Demolition
on 20,633 square yards of bridge deck surface. Place 1 1/4 inches of
Latex Concrete wearing surface.
INDIANA: Project B-23329, Lake Co., East Chicago,
Indiana.
Description: Perform Total Surface Preparation using Hydro-Demolition
on 3,714 M2 of bridge deck surface. Place a new Latex Concrete wearing
surface.
KENTUCKY: Project 60382, I-75, Whitley Co.
Description: Perform Total Surface Preparation using Hydro-Demolition
on 7,918 square yards of bridge deck surface and place a new “Rapid
Set” Latex Concrete overlay.
WEST VIRGINIA: Project: S331-7-36.60, Monongalia Co.
Description: Perform Total Surface Preparation using Hydro-Demolition
and place a new Latex Concrete overlay.
TENNESSEE: Project: 5764, Marion Co., I-24 over Tennessee
River.
Description: Perform Total Surface Preparation using Hydro-Demolition
and place a new Latex Concrete overlay on 17,335 square yards of bridge
deck surface.
INDIANA: Projects: B-24017, B-24015, B-24014, SR 37,
Monroe Co.
Description: Perform Total Surface Preparation using Hydro-Demolition
on 9,366 M2 of bridge deck surface and place a new Latex Concrete overlay.
KENTUCKY: I-75 Brent Spence Bridge Overlay
Description: Remove 17,300 Square Yards of Low Slump overlay
@ 1 3/4 inches. Perform Total Surface Hydro-Demolition Surface Preparation.
Place new 1 3/4 inch Latex concrete overlay.
Job Highlights: Double deck structure is the heaviest traveled
structure in the Commonwealth of Kentucky. All construction joints replaced.
Entire project completed in record time of 32 work days. For more information
about this project call:
TENNESSEE: I-40 Bridge, Nashville
Two phases, 2,400 square yards of Total Surface Hydro-Demolition Surface
Preparation. Place new Latex concrete overlay.
Job Highlights: Only way to access I-40 to Memphis. 30 days
to complete project. Project was completed in 19 work days. For more
information about this project call:
PENNSYLVANIA: PENNDOT Project CMS 111533, SR 79, Allegheny
Co.
Job Description: Hydro-Demolition Surface Preparation and installing
new Latex concrete overlay. For more information call:
TENNESSEE: Tennessee Valley Authority Project PPW-226000,
Job Description: Pickwick Dam Bridge Repairs, 11,421 square
yards. Remove existing low slump overlay, perform Hydro-Demolition Surface
Preparation and install new Latex concrete overlay. Project start date
May 4, 1998 to July 3, 1998. For more information call:
LOUISIANA: LDOT Project IM-20-1(209) 019 (Ramp), RT.
I-20 over Red River in Shreveport - Bossier City.
Job Description: Hydro-Demolition Surface Preparation and install
new Latex concrete overlay - 2,222 square yards. 6 days to complete
job.
TEXAS: Awaiting write up...
NORTH CAROLINA : Awaiting write up...
MISSOURI: Awaiting write up...